  • LocationLeamington Spa
  • Duration
    19 weeks
  • Value£4.3 million

Cat B office fit-out to the 1st & 2nd floor offices, tailored to meet the client’s high-specification requirements. Works included full architectural project design, full M&E installation, structural alterations for a new staircase and mezzanine, partitioning, flooring, decoration, furniture, and two new disabled lifts.

McCarthys were engaged from initial design to final completion, delivering the 19-week project efficiently by programming both floors consecutively. Design workshops and weekly meetings ensured the deadline was met despite the challenges.

Related Projects

View all projects

Fit-out

Karting Centre Rollout Programme

Principal contractor, CDM and contracted works roles on demolition, strip out, building...

View Project

Build

Birmingham Metropolitan

McCarthys was appointed by Birmingham Metropolitan as Principal Contractor to roll out a programme...

View Project

Build

EcoPark

McCarthys completed a New Build project at the Eco Park in Birmingham for The Wildlife Trust...

View Project

Fit-out

Knight Frank Investment Management

The main priority for this project was to create a workspace that centred on physical and...

View Project

Fit-out

NeuroClin

Cat B fit out to create a Clinical Research Facility. McCarthys completed a fast-track turn key...

View Project

Fit-out

Sega Leamington Spa

Following the successful completion of a previous fit-out McCarthys were engaged by SEGA...

View Project

Fit-out

Eurokey

Works comprise of a fit out of a new warehouse to operate as a recycling facility. This was the...

View Project
Show Cookie Preferences